Previous year question hub

Estimation, Costing and Building Economics - Project Management and Professional Practice - Architecture and Planning Previous Year Questions

Practice Estimation, Costing and Building Economics - Project Management and Professional Practice - Architecture and Planning previous year questions organised from real papers, with year-wise coverage and clear topic navigation.

16Papers
16Years
42Questions
1Topics

Estimation, Costing and Building Economics question pattern

Every graph below is calculated only from this selection.

Questions by year

Compare question counts across years.

Difficulty distribution

How the classified questions are distributed by difficulty.

Easy 28 66.7%
Medium 14 33.3%

Question type distribution

MCQ, numerical, multiple-select and other formats found in these papers.

Numerical Answer Type (NAT) 23 54.8%
MCQ 18 42.9%
Fill in the blanks 1 2.4%

Subject weightage

Top subjects by unique question coverage.

Architecture and Planning
42 Qs

Most asked topics

Top topics across the included previous year papers.

Project Management and Professional Practice
42 Qs

Subtopic coverage

Top subtopics inside this exact selection.

Estimation, Costing and Building Economics
42 Qs

Paper coverage

Question coverage for the most populated papers. Every active PYP paper remains listed below.

Architecture and Planning (AR) 2026
3 Qs
Architecture and Planning (AR) 2025
1 Qs
Architecture and Planning (AR) 2024
4 Qs
Architecture and Planning (AR) 2023
2 Qs
Architecture and Planning (AR) 2022
2 Qs
Architecture and Planning (AR) 2021
3 Qs
Architecture and Planning (AR) 2019
2 Qs
Architecture and Planning (AR) 2018
2 Qs
Architecture and Planning (AR) 2017
2 Qs
Architecture and Planning (AR) 2016
3 Qs
Architecture and Planning (AR) 2014
3 Qs
Architecture and Planning (AR) 2013
3 Qs
Architecture and Planning (AR) 2011
3 Qs
Architecture and Planning (AR) 2010
2 Qs
Architecture and Planning (AR) 2008
5 Qs
Architecture and Planning (AR) 2007
2 Qs

Included previous year papers

Newest papers appear first. Search these papers or sort by year and name.

Paper nameYearPDFAttempt
Architecture and Planning (AR) 20262026
3 questions in this view
2026
Architecture and Planning (AR) 20252025
1 questions in this view
2025
Architecture and Planning (AR) 20242024
4 questions in this view
2024
Architecture and Planning (AR) 20232023
2 questions in this view
2023
Architecture and Planning (AR) 20222022
2 questions in this view
2022
Architecture and Planning (AR) 20212021
3 questions in this view
2021
Architecture and Planning (AR) 20192019
2 questions in this view
2019
Architecture and Planning (AR) 20182018
2 questions in this view
2018
Architecture and Planning (AR) 20172017
2 questions in this view
2017
Architecture and Planning (AR) 20162016
3 questions in this view
2016
Architecture and Planning (AR) 20142014
3 questions in this view
2014
Architecture and Planning (AR) 20132013
3 questions in this view
2013
Architecture and Planning (AR) 20112011
3 questions in this view
2011
Architecture and Planning (AR) 20102010
2 questions in this view
2010
Architecture and Planning (AR) 20082008
5 questions in this view
2008
Architecture and Planning (AR) 20072007
2 questions in this view
2007

All Estimation, Costing and Building Economics previous year questions

Practice every matching question in batches of 20, with every available option.

1
2007 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2007
A house was constructed 20 years ago at a cost of Rs. 1,00,000. The estimated life of the building is 50 years, at the end of which it will have a 15 % scrap value of its cost of construction. Its present value in Rupees is
Open complete paper
2
2007 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2007
If the reinforcement steel provided for a RCC slab of volume 15.0 cu.m. is @ 1%, then the quantity of steel required in kilograms is
Open complete paper
3
2008 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2008
What would be the total outgoings in Rs.?
Open complete paper
4
2008 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2008
What would be the net annual rent in Rs.?
Open complete paper
5
2008 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2008
If the Years Purchase in perpetuity comes out to be 12.5, what would be the capitalized value, in Rs. of the above building?
Open complete paper
6
2008 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2008
Identify the relationship governing the cost of land (C) based on the following factors:
Net density in plots per hectare = p
Land use percentage allocation in net housing = q
Price of land in Rs. per sq m = s
Open complete paper
7
2008 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2008

If for a housing development, p = 30, q = 45 and s = 500, then the cost of land per dwelling unit is:

Open complete paper
8
2010 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2010
The total amount of sinking fund at the end of 20 years will be
Open complete paper
9
2010 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2010
If the rate of interest is 7 %, then the annual installment of sinking fund will be
Open complete paper
10
2011 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2011

Residual method of valuation is used to determine

Open complete paper
11
2011 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2011
The maintenance cost of a building will be Rs.2 lacs after 10 years. The annual sinking fund required for such maintenance @ 6 % interest per annum will be
Open complete paper
12
2011 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2011
The variable cost (V) of manufacturing a product varies according to the equation V= 4q, where q is the quantity produced. The fixed cost (F) of production of same product reduces with q according to the equation F = 100/q. How many units should be produced to minimize the total cost (V+F)?
Open complete paper
13
2013 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2013
Cost of a new building is Rs 10,00,000 and its scrap value after 50 years is Rs. 1,00,000. Using straight line method
The annual depreciation of the building in Rs. would be
Open complete paper
14
2013 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2013

The book value after 10 years in Rs. would be

Open complete paper
15
2013 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2013
A firm is selling its product at Rs. 60 per unit. The total cost of production is Rs. 100 and firm is earning total profit of Rs. 500. Later, the total cost increased by 30%. By what percentage the price should be increased to maintained the same profit level.
Open complete paper
16
2014 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2014
A housing project is proposed to be designed in a plot of 2 hectare. Maximum permissible FAR is 2. The share of the numbers of dwelling units (DU) for MIG, LIG and EWS is 1:2:3 having sizes of 55, 35 and 25 sq.m respectively. The maximum number of DU which can be accommodated in the plot is ______
Open complete paper
17
2014 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2014
A neighborhood has 250 units of 80 sq.m each and 200 units of 100 sq.m each. If the mandatory parking requirement is one per 100 sq.m of built space then, the total area(sq.m) required for parking considering 30 percent additional area for circulation is ______
Open complete paper
18
2014 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2014
From the following cost components of a building construction project which is not a direct cost combination?
P. Labour cost
Q. Equipment cost
R. Material cost
S. Establishment cost
T. Supervision cost
Open complete paper
19
2016 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2016
One litre of acrylic paint can cover 16 sqm of wall area for the first coat and 24 sqm for the second coat. The walls of a lecture hall measuring 12m × 8m × 4m (L × B × H) need to be painted with two coats of this paint. The hall has total glazed fenestration area of 12 sqm. The number of 4 litre paint containers required will be ____________________
Open complete paper
20
2016 · Architecture and Planning · Project Management and Professional Practice · Estimation, Costing and Building Economics
Architecture and Planning (AR) 2016
A solar photo-voltaic system is proposed to be installed at the roof top of a hostel. The cost of installation and the annual maintenance are INR 2,40,000 and INR 6000 respectively. It is expected to generate 600 kWh of electricity per month. Assume unit price of electricity as INR 5. Ignoring the discount rate, the payback period of the investment in years is____________________
Open complete paper

Showing 20 of 42 questions