ESE (IES) Mechanical Engineering P2 2015

Review the key details, then start the test when you are ready. You can also open the full package to see related papers.

Questions 120
Duration 180 mins
Package ESE & GATE ME - Previous Year Papers

Paper pattern & analysis

Filter this paper by subject, topic or subtopic. Every graph updates from the selected questions.

Explore previous papers
Showing all 120 questions in this paper.

Subject distribution

No subject classification is available.

Topic distribution

No topic classification is available.

Subtopic distribution

No subtopic classification is available.

Difficulty distribution

Medium 86 71.7%
Hard 19 15.8%
Easy 15 12.5%

Question type distribution

Multiple Choices 120 100%

Instructions

Demo Instruction

Syllabus

Sample

Sample questions from this paper

Questions are selected across the paper subjects wherever the paper contains that variety.

1
2015 · Unclassified
ESE (IES) Mechanical Engineering P2 2015
Which of the following statements apply to provision of flash gutter and flash land around the parts to be forged? 1. Small cavities are provided which are directly outside the die impression. 2. The volume of flash land and flash gutter should be about 20%-25% of the volume of forging. 3. Gutter is provided to ensure complete closing of the die.
A
1 and 2 only
B
1 and 3 only
C
1, 2 and 3
D
2 and 3 only
2
2015 · Unclassified
ESE (IES) Mechanical Engineering P2 2015
A hole and a shaft have a basic size of 25 mm, and are to have a clearance fit with a maximum clearance of 0.02 mm and a minimum clearance of 0.01 mm. The hole tolerance is to be 1.5 times the shaft tolerance. The limits of both hole and shaft using hole basis system will be
A
low limit of hole = 25 mm, high limit of hole = 25.006 mm, upper limit of shaft = 24.99 mm and low limit of shaft = 24.986 mm
B
low limit of hole = 24 mm, high limit of hole = 25.006 mm, upper limit of shaft = 25 mm and low limit of shaft = 24.99 mm
C
low limit of hole = 25.006 mm, high limit of hole = 25 mm, upper limit of shaft = 24.99 mm and low limit of shaft = 25 mm
D
low limit of hole = 25 mm, high limit of hole = 25.026 mm, upper limit of shaft = 24.8 mm and low limit of shaft = 24.76 mm
3
2015 · Unclassified
ESE (IES) Mechanical Engineering P2 2015
Consider the following statements: In case of assembly of mating parts 1. the difference between hole size and shaft size is called allowance 2. in transition fit, small positive or negative clearance between the shaft and hole member is employable Which of the above statements is/are correct?
A
1 only
B
Both 1 and 2
C
2 only
D
Neither 1 nor 2
4
2015 · Unclassified
ESE (IES) Mechanical Engineering P2 2015
An organization has decided to produce a new product. Fixed cost for producing the product is estimated as Rs. 1,00,000. Variable cost for producing the product is Rs. 100. Market survey indicated that the product selling price could be Rs. 200. The break-even quantity is
A
1000
B
500
C
900
D
2000
5
2015 · Unclassified
ESE (IES) Mechanical Engineering P2 2015
Using exponential smoothening, a car manufacturing company predicted the demand for the year as 1040 cars. The actual sale was found to be 1140 cars. If the company’s forecast for the next year is 1080, what is the value of the smoothing constant?
A
0.4
B
0.7
C
1.2
D
0.6
6
2015 · Unclassified
ESE (IES) Mechanical Engineering P2 2015
Coarse feed, low rake angle, low cutting speed and insufficient cooling help produce
A
continuous chips in ductile materials
B
discontinuous chips in ductile materials
C
continuous chips with built-up edges in ductile materials
D
discontinuous chips in brittle materials